On July 24, 2025, the Oregon Public Utility Commission (Commission) issued an order conditionally acknowledging Portland General Electric’s (PGE) proposed 2025 All-Source Request for Proposals (RFP) for new generating resources. Acknowledgment is akin to a determination that the RFP is reasonable at the time of the Commission’s decision, and the acknowledgment decision will make it easier for PGE to recover costs of any resources ultimately procured from this RFP later in customer rates. [Read more…]
Archives for July 2025
Washington Commission Approves Avista’s 2025 RFP
July 1, 2025 By
At the May 22, 2025 Open Meeting, the Washington Utilities and Transportation Commission (the Washington Commission) approved Avista’s 2025 Request for Proposals (RFP) with conditions in Docket No. UE-250155. The order approving the RFP was issued on May 23, 2025. [Read more…]